工程管理 外文翻譯 外文文獻(xiàn) 英文文獻(xiàn) 淺談工程索賠的預(yù)防與處理
《工程管理 外文翻譯 外文文獻(xiàn) 英文文獻(xiàn) 淺談工程索賠的預(yù)防與處理》由會(huì)員分享,可在線閱讀,更多相關(guān)《工程管理 外文翻譯 外文文獻(xiàn) 英文文獻(xiàn) 淺談工程索賠的預(yù)防與處理(9頁珍藏版)》請(qǐng)?jiān)谘b配圖網(wǎng)上搜索。
1、Talking about the project claim the prevention and treatment Abstract:In project management, construction claim is a complex business management. Todays domestic project contracting market is becoming more competitive, successful low-cost has become a regular operation, the operating contractor
2、 for the construction of the claim is very important to achieve the goal. The significance of the claim and described the concept for todays domestic construction projects in claims management problems were analyzed and the corresponding countermeasures and suggestions of the project and counter-cla
3、ims both sides claim the contract is an indispensable business component. Based on the analysis of the factors that claims the project, discussed the contract on the implementation of the project claim the deal with the principles and specific treatment. Key words: engineering claim prevention
4、 deal with 1. The definition and classification of claims Claim the project is the fulfillment of the contract, the contract due to the other party did not fulfill its obligations under the contract and this led to losses, other demands for compensation or the right to compensation. The incid
5、ence of claims is a two-way, as long as the contract side of the responsibility and obligation not to achieve contract, or to provide the conditions inconsistent with the contractual status, there are claims that may arise. It is also a kind of a right, under normal circumstances, the claim refers t
6、o the contractor in the implementation of the contract process, the reasons for their non-extension of the project, and require owners to increase the cost of compensation for the loss of a claim. The owners belong to the construction unit should bear the responsibility for the cause, and the actual
7、 loss to the construction of requests for compensation, known as the anti-claim. 1.1 The purpose of their claims can be divided into two categories: construction claims and claims costs. Claim Construction Engineering refers to, as a result of non-responsibility of the contractor causes delay in t
8、he construction process for approval of the contract extended period of the claim. Construction units of the purpose of the claim period is usually two: first, removed or have been shirking its responsibility to extend the duration of the contract responsibility, so that they do not pay as much as p
9、ossible or not to extend the time limit to pay fines; II is due to extension of the period and The cost of damage caused by the claim. If the project is not the responsibility of delay caused by the construction, and construction units have been approved construction project claim, the construction
10、units can be made as a result of measures taken to speed up and increase the cost of claims. The cost of claims is based on the principle of compensation for actual losses, and its purpose is to require financial compensation. When the reality of the conditions of the contract and inconsistent, lead
11、ing to increase in contractor expenses in excess of the requirements of the plans cost of the additional compensation expenses, in order to save his commitment should not be economic losses. 2.The cause of the project claim 2.1 Engineering design arising from claims. As the construction draw
12、ings in error or defective, working drawings and the actual construction site in geology, environment, or the difference between the design drawings and specifications does not match the description of expression is not tight construction, equipment, materials, the name of the model specifications t
13、hat Or the wrong amount of work is not clear and many other aspects of the flaws and omissions, resulting in rework. Inevitable in order to produce in the period, the labor, materials, and other aspects of the claims. 2.2 Do not close the signing of the contract arising from claims The contract
14、 is a contract agreement, the tender documents, tender, contract-specific provisions, general provisions of the contract, drawings, BOQ and to fulfill the contract in the course of a series of supplementary agreements such as the composition of the document, the contracts signed between the two side
15、s in accordance with the law The entry into force, legally binding, either party may change or dissolve the non-performance of the contract or the powers and duties. However, due to construction projects and the complexity of the construction period, as well as the natural environment, climate, such
16、 as long-term factors, together with the terms of the contract in terms of security is not strong, between the conflicting documents, are likely to make the parties enter into the Construction contracts can not take full account of all factors and a clear impact on the project, which led to the cons
17、truction of the claim. 2.3 The risk of accidents and unforeseen factors such as changes in the conditions of the claim During the construction process, changes in the conditions of the construction site of the project cost and impact, such as earthquakes, typhoons, war, rebellion, radioactive poll
18、ution and nuclear hazards, such as force majeure risks and natural disasters as well as the construction of sand mud emerged, geological Fault, natural cave, subsidence and underground structures or objects on the ground floor, and other unknown obstacles, often leading to the changes caused by the
19、construction claim. If excavation works due to the discovery of underground structures and cultural relics, and so on, the drawings did not say construction indeed difficult to foresee a reasonable man-made obstacles, such as the deal is bound to lead to an increase in the cost of the project, the c
20、onstruction units can claim. 2.4 Project construction contracts management changes in the claim. The current construction market, the project construction contracts have a total package, sub-, sub-designate, contract labor, equipment, materials supply contract and a series of contract, so as to en
21、able the project construction contracts and management has become complicated by the difficulty Great. When any of the contracts can not perform well or poorly managed, will affect the project construction period, the quality and quantity, sparking the project, quality, quantity and economic aspects
22、 of the claim. Such as equipment, material suppliers, according to the projects design and construction schedule on time in accordance with the provision of quality equipment, materials, engineering, can not by the owners of the requirements and design specifications and the specifications for the c
23、onstruction, so as to affect the project construction The progress and quality, leading to the owners, with a total package side, the sub-side, the equipment and materials suppliers mutual claims. 3Works to prevent and deal with the claims. 3.1The project Prevention claims Of the above factor
24、s in the analysis of the project claim, the claim works, as owners of the management of the main square in the prevention and treatment efforts must be dealt with the principles and specific ways to deal with, making a reasonable claim for compensation evidence to ensure the progress of the construc
25、tion project, quality, the cost of a virtuous circle. Should do the following specific areas: 3.1.1To strengthen the claim of forward-looking prevention. As owners, supervision engineers and contractors must use their experience and the relevant regulations, to take active measures to prevent fores
26、eeable claims the incident occurred. Such as strengthening the management of the contract, to strengthen preparatory work to strengthen the design review, and so on. However, if the claim is indeed taken place, should take active measures to control claims costs to a minimum. 3.1.2In market economy
27、 conditions, the contract is binding both A and B criterion of economic behavior. As the owners managers should pay attention to fully and strictly carry out the contract. Before signing the contract should be repeated, as appropriate, the terms of the contract, pay attention to the strict letter of
28、 the contract documents, in order to prevent the implementation of the contract process as a result of loopholes in the text caused by the opportunity to claim, resulting in additional investment. In the design of management should strive to obtain the contract by design drawings, data, and un
29、its designed to improve the quality of design, conditions permitting the introduction of the design competition, designed to improve the quality of service. 〖JP2〗through the design of the credibility of the tender selection, design, management capacity in areas such as better design of the unit, des
30、igned to reduce as much as possible the reasons for increase in the risk of project cost, the latter designed to improve the quality of service. 3.1.3 In the supply of materials, equipment and materials should be done on time and the supply, quality volume. As far as possible to avoid the supply of
31、 material specifications of the type, variety and not caused by the drawings of alternative materials. 3.1.4 The price may rise to the claim by the construction tender will be taken to increase the risk of a package as a death order to guard against the practice, that is, in business contracts, acc
32、ording to the length of period, the market price trend forecast, the two sides to agree on a cost risk To the contractors and contract during the construction of national and local government policy documents are no longer the implementation of price adjustment. 3.2 Engineering claims. 3.2.1 Sho
33、uld be based on a contract basis to deal with claims must be reasonable; have to pay attention to data collection, information truthfulness, reliability, and after that must deal with claims in a timely manner; in dealing with the specific claims process, we must A close examination of the period wh
34、en the claims should be given, should be given when the cost of claims. For example: an extremely bad weather conditions, we have exceeded the expected normal rain and snow, seriously hampering the progress of projects at this time, the construction units may be required, the owner can grant an exte
35、nsion period, that is, the establishment of the claim period, but the cost should not be Claim. For instance, in the works in full swing during part of the project changes, construction has been finished on the part of the change and wait for the drawings when part of the construction and mechanical
36、 requirements of the claim, this time, to have been part of the End of the claim, it should benefit all, Including the costs and profits, but stagnation and machinery, due to the time when the construction season, it is entirely possible that this first part of the personnel, machinery to use elsewh
37、ere, to be paid should be the only change of duty and the types of work efficiency to lower costs. 3.2.2 To deal with claims in the event of limitations should be carried out inspection, the building of Chinas construction contracts (GF-1999-2001) in the light of international common FIDIC conditio
38、ns of contract claim against the statute of limitations provides as follows: "The claim occurred within 28 days of Engineers to issue a claim Notice; issued a notice of claim within 28 days to raise additional engineers to extend the duration of the contract price or the claims report and related in
39、formation; engineers sent to the contractor received the report and claims information after the 28 days given to sign rehabilitation, Or ask the contractor to add further grounds for the claim and evidence. Engineers in 28 days or did not respond to the contractor for further requirements, as the c
40、laims have been approved. " Excess of the limitation period for claims, as the case may have the right to refuse. At the same time, the claim should be effective to deal with in a timely manner. 3.2.3 Should clearly define the responsibilities, strict examination fees. The claim of actual events a
41、re often responsible for both contracts, which should identify the reasons, clearly define responsibilities and in accordance with the terms of the contracts pricing review to determine the contract that both sides should bear the cost. 3.2.4Should work to strengthen the control of the initiative,
42、works to reduce the claim. This requires the owners in project management, as far as possible the work should be made in advance, to reduce the incidence of claims. This will enable the project to carry out more smoothly, reducing investment projects to reduce the construction period. To sum up, the
43、 claim for the prevention and management of investment projects to control play an important role in the international engineering construction in general will be designed to claim the contract price of 10-15% in individual cases even more. In order to better handle the construction of the claims th
44、e problem from the project to strengthen the construction plans and construction contract management, strengthen personnel training to start, actively explore and practice. References [1] Wu Yuan, Wu Yin, Chinas construction industry, claims the status quo and countermeasures [J]. Economist,
45、 2006, (3). [2] Xu Wei, Jin Fu, Chen Lianjie. Standardize the implementation of the construction project supervision Manual [M]. Beijing: China Building Industry Press, 2001. [3] Dong Cheng Hai, Zhang Jiansheng. Analysis of Construction Contract Management Problems and Solutions [J]. Mod
46、ernization construction management, 2001, (1). [4] Cheng Hu. Encyclopedia of Practical construction contract management [M]. Beijing: China Building Industry Press, 2000, (1). 淺談工程索賠的預(yù)防與處理 學(xué) 生:張 曦 指導(dǎo)教師:王春燕 三峽大學(xué)科技學(xué)院 摘要: 在工程項(xiàng)目管理中,施工索賠是一項(xiàng)復(fù)雜的經(jīng)營管理工作。當(dāng)今國內(nèi)工程項(xiàng)目承包市場(chǎng)競(jìng)爭(zhēng)日趨激烈,
47、低價(jià)中標(biāo)已成為規(guī)律性的操作方式,施工索賠對(duì)于承包商經(jīng)營目標(biāo)實(shí)現(xiàn)非常重要。 對(duì)索賠的意義和概念進(jìn)行了闡述,對(duì)當(dāng)今國內(nèi)施工項(xiàng)目索賠管理中存在的問題進(jìn)行了分析,并提出了相應(yīng)的對(duì)策和建議工程索賠與反索賠是合同雙方經(jīng)營活動(dòng)不可缺少的組成部分。本文通過對(duì)工程索賠因素的分析,論述了在合同執(zhí)行中關(guān)于工程索賠相應(yīng)的處理原則及具體的處理方式。 關(guān)鍵詞:工程;索賠;預(yù)防;處理 1 索賠的定義及分類 索賠是指在工程承包合同履行中,合同當(dāng)事人一方由于另一方未履行合同所規(guī)定的義務(wù)而致使本方遭受損失時(shí),要求對(duì)方給予賠償或補(bǔ)償?shù)臋?quán)利。索賠的發(fā)生是雙向的,只要合同中一方的責(zé)任和義務(wù)未按合同約定實(shí)現(xiàn),或出現(xiàn)提供的條件
48、與合同約定狀態(tài)不一致,都有可能出現(xiàn)索賠。它既是一種權(quán)利也是一種行為,通常情況下,索賠是指承包商在合同實(shí)施過程中,對(duì)非自身原因造成的工程延期、費(fèi)用增加而要求業(yè)主給予補(bǔ)償損失的一種權(quán)利要求。而業(yè)主對(duì)于屬于施工單位應(yīng)承擔(dān)責(zé)任造成的,且實(shí)際發(fā)生了損失,向施工單位要求的賠償,稱為反索賠。 1.1 索賠按其目的可分為兩類:工期索賠和費(fèi)用索賠。 工期索賠是指在工程施工中,由于非承包人責(zé)任的原因而導(dǎo)致施工進(jìn)程延誤,要求批準(zhǔn)順延合同工期的索賠。施工單位提出工期索賠的目的通常有兩個(gè):一是免去或推卸自己對(duì)已產(chǎn)生的工期延長的合同責(zé)任,使自己不支付或盡可能不支付工期延長的罰款;二是進(jìn)行因工期延長而造成的費(fèi)用損失的索
49、賠。如果工期延緩責(zé)任不是由施工單位造成,而建設(shè)單位已認(rèn)可施工單位工期索賠,則施工單位還可以提出因采取加速措施而增加的費(fèi)用索賠。費(fèi)用索賠是以補(bǔ)償實(shí)際損失為原則,其目的是要求經(jīng)濟(jì)補(bǔ)償。當(dāng)現(xiàn)實(shí)的條件與合同約定不一致,導(dǎo)致承包商增加開支,要求對(duì)超出計(jì)劃成本的附加開支給予補(bǔ)償, 以挽回不應(yīng)由他承擔(dān)的經(jīng)濟(jì)損失。 2 工程索賠的發(fā)生原因 2.1要程設(shè)計(jì)方面引起的索賠 由于施工圖紙中存在缺陷或錯(cuò)誤,施工圖與現(xiàn)場(chǎng)實(shí)際施工在地質(zhì)、環(huán)境等方面的差異或是設(shè)計(jì)的圖紙與規(guī)范要求不符,施工說明表達(dá)不嚴(yán)密,對(duì)設(shè)備、材料的名稱、規(guī)格型號(hào)表示不清楚或工程量錯(cuò)誤等諸多方
50、面的遺漏和缺陷,造成返工。從而不可避免的產(chǎn)生如在工期、人工、材料等方面的索賠要求。 2.2合同簽訂不嚴(yán)密引起的索賠 合同是由合同協(xié)議書、招標(biāo)文件、投標(biāo)書、合同專用條款、合同通用條款、圖紙、工程量清單及合同履行過程中的補(bǔ)充協(xié)議等一系列的文件所組成的,經(jīng)承發(fā)包雙方依法簽訂生效,具有法律約束力,任何一方不得擅自變更或解除或不履行合同賦予的權(quán)力和義務(wù)。但由于工程項(xiàng)目建設(shè)的復(fù)雜性和施工工期以及自然環(huán)境、氣候、周期長等因素的限制,加上合同中用詞嚴(yán)密性不強(qiáng)、文件之間的相互矛盾等,都有可能使雙方在簽訂施工合同時(shí)不能充分考慮和明確各種因素對(duì)工程建設(shè)的影響,從而引起施工索賠。 2.3 意外風(fēng)險(xiǎn)和不可預(yù)見因素
51、等條件的變化引起的索賠 在施工過程中,施工現(xiàn)場(chǎng)條件的變化對(duì)工期和造價(jià)影響很大,如地震、臺(tái)風(fēng)、戰(zhàn)爭(zhēng)、叛亂、放射性污染、核危害等人力不可抗拒的自然災(zāi)害和風(fēng)險(xiǎn)以及在施工中出現(xiàn)流沙泥、地質(zhì)斷層、天然溶洞、沉陷和地下文物或構(gòu)筑物等地下不明障礙物,常常導(dǎo)致工程變更,引起施工索賠。如在挖方工程中由于發(fā)現(xiàn)地下構(gòu)筑物和文物等,圖紙上并未說明,確屬施工單位難以合理預(yù)見的人為障礙,如處理則必然導(dǎo)致工程費(fèi)用的增加,施工單位即可提出索賠。 2.4工程項(xiàng)目建設(shè)承發(fā)包管理模式變化引起的索賠 當(dāng)前的建筑市場(chǎng),工程項(xiàng)目建設(shè)承發(fā)包有總包、分包、指定分包、勞務(wù)承包、設(shè)備、材料供應(yīng)承包等一系列的承包方式,使工程項(xiàng)目建設(shè)承發(fā)包變
52、得復(fù)雜和管理模式難度增大。當(dāng)任何一個(gè)承包合同不能順利履行或管理不善時(shí),都會(huì)影響工程項(xiàng)目建設(shè)的工期、質(zhì)量和數(shù)量,繼而引發(fā)在工期、質(zhì)量、數(shù)量和經(jīng)濟(jì)等方面的索賠。如設(shè)備、材料供應(yīng)商不按工程項(xiàng)目的施工進(jìn)度和設(shè)計(jì)要求按時(shí)按質(zhì)提供設(shè)備、材料,工程也就不能按業(yè)主的要求和設(shè)計(jì)的質(zhì)量規(guī)格以及有關(guān)規(guī)范要求進(jìn)行施工,從而影響工程項(xiàng)目建設(shè)的進(jìn)度和質(zhì)量,最終導(dǎo)致業(yè)主、總包方、分包方、設(shè)備材料供應(yīng)商相互間的索賠。 3 工程索賠的預(yù)防及處理 3.1工程索賠的預(yù)防 通過以上對(duì)工程索賠因素的分析,對(duì)于工程索賠,作為業(yè)主方的管理主要是在預(yù)防和處理方面下功夫,必須要有相應(yīng)的處理原則及具體的處理方式,使得索賠合理,賠償有據(jù),以
53、確保建設(shè)工程項(xiàng)目的進(jìn)度、質(zhì)量、費(fèi)用的良性循環(huán)。具體應(yīng)做好以下幾方面: 1)加強(qiáng)索賠的前瞻性預(yù)防。作為業(yè)主、監(jiān)理工程師和承包商,都要借助自己的經(jīng)驗(yàn)和有關(guān)規(guī)定,采取積極的措施防止可以預(yù)見的索賠事件的發(fā)生。如加強(qiáng)合同管理、加強(qiáng)前期準(zhǔn)備工作、加強(qiáng)對(duì)設(shè)計(jì)方案的審查等等。但如果索賠確實(shí)發(fā)生了,應(yīng)積極采取措施,把索賠費(fèi)用控制在最小范圍之內(nèi)。 2)在市場(chǎng)經(jīng)濟(jì)條件下,合同是約束甲乙雙方經(jīng)濟(jì)行為的準(zhǔn)繩。作為業(yè)主方的管理人員應(yīng)注意全面、嚴(yán)格地履行合同。合同在簽約前應(yīng)反復(fù)斟酌合同條款,注重合同文件文字的嚴(yán)密性,以防止在實(shí)施合同過程中因文字漏洞而造成索賠機(jī)會(huì),從而導(dǎo)致額外投資。 在設(shè)計(jì)管理方面應(yīng)努力做到按合同規(guī)定
54、索要設(shè)計(jì)圖紙、資料,并要求設(shè)計(jì)單位提高設(shè)計(jì)質(zhì)量,在條件允許的情況下引入設(shè)計(jì)競(jìng)爭(zhēng)機(jī)制,提高設(shè)計(jì)服務(wù)質(zhì)量?!糐P2〗通過設(shè)計(jì)招標(biāo)選擇在信譽(yù)、設(shè)計(jì)水平、管理能力等方面較好的設(shè)計(jì)單位,盡可能地減少因設(shè)計(jì)原因增加工程造價(jià)的風(fēng)險(xiǎn),提高設(shè)計(jì)后期服務(wù)質(zhì)量。 3)在物資供應(yīng)方面,應(yīng)做到設(shè)備和材料供應(yīng)按時(shí),保質(zhì)保量。盡量避免因材料供應(yīng)的規(guī)格型號(hào)、品種與圖紙不符而造成材料代用。 4)對(duì)于物價(jià)上漲可能引起的索賠,可以通過施工招標(biāo)、采取將漲價(jià)作為風(fēng)險(xiǎn)一次包死的作法來加以防范,即在商簽合同時(shí),根據(jù)工期長短、市場(chǎng)物價(jià)走勢(shì)的預(yù)測(cè),雙方商定一個(gè)風(fēng)險(xiǎn)費(fèi)用給承包商,并在合同中規(guī)定建設(shè)期間國家、地方政府的政策性調(diào)價(jià)文件一律不再執(zhí)
55、行。 3.2工程索賠的處理 1)應(yīng)以合同為依據(jù),處理索賠時(shí)必須做到有理有據(jù);必須注意資料的收集、對(duì)資料的真實(shí)性、可信度,必須認(rèn)定后及時(shí)地處理索賠;在具體處理索賠的過程中,一定要仔細(xì)分析,什么時(shí)候應(yīng)該給工期索賠,什么時(shí)候應(yīng)該給費(fèi)用索賠。比如:天氣條件極其惡劣,已超出了我們預(yù)想的正常雨雪天氣,嚴(yán)重阻礙了工程的進(jìn)展,這個(gè)時(shí)候,施工單位可以要求,業(yè)主也可以批準(zhǔn)延長工期,即工期索賠成立,但不應(yīng)出現(xiàn)費(fèi)用索賠。再比如,在工程的全面展開時(shí)期,部分工程發(fā)生變更,施工單位對(duì)變更已完部分及等待圖紙時(shí)該部分的施工人員及機(jī)械要求索賠,此時(shí),對(duì)于已完部分的索賠,應(yīng)該全部給付,其中包括成本和利潤,但對(duì)于停滯的人員和機(jī)械
56、,由于正值施工旺季,完全可以先把此部分人員、機(jī)械調(diào)到別處使用,所應(yīng)賠付的應(yīng)該只是更換工作地點(diǎn)及工種的工效降低費(fèi)。 2)在處理索賠事件時(shí)應(yīng)進(jìn)行時(shí)效檢查,我國建設(shè)工程施工合同文本(GF— 1999—2001)參照國際上通用的FIDIC合同條件對(duì)索賠的時(shí)效作了如下規(guī)定:“索賠發(fā)生28天內(nèi),向工程師發(fā)出索賠意向通知;發(fā)出索賠意向通知后28天內(nèi),向工程師提出追加合同價(jià)款或延長工期的索賠報(bào)告及有關(guān)資料;工程師在收到承包商送交的索賠報(bào)告和有關(guān)資料后,于28天內(nèi)給予簽復(fù),或要求承包商進(jìn)一步補(bǔ)充索賠理由和證據(jù)。工程師在28天內(nèi)未給予答復(fù)或未對(duì)承包商作進(jìn)一步要求,視為該項(xiàng)索賠已經(jīng)認(rèn)可”。對(duì)于超出規(guī)定時(shí)效期限的索
57、賠,視具體情況有權(quán)拒絕。同時(shí)對(duì)有效索賠應(yīng)及時(shí)處理。 3)應(yīng)分清責(zé)任,嚴(yán)格審核費(fèi)用。對(duì)實(shí)際發(fā)生的索賠事件,往往是合同雙方均負(fù)有責(zé)任,對(duì)此要查明原因,分清責(zé)任,并根據(jù)合同規(guī)定的計(jì)價(jià)方式進(jìn)行審核,以確定合同雙方應(yīng)承擔(dān)的費(fèi)用。 4)應(yīng)在工作中加強(qiáng)主動(dòng)控制,減少工程索賠。這就要求業(yè)主在工程管理過程中,應(yīng)當(dāng)盡量將工作做在前面,減少索賠事件的發(fā)生。這樣能夠使工程更順利地進(jìn)行,降低工程投資,減少施工工期。 綜上所述,索賠的預(yù)防和處理對(duì)于工程投資控制起著相當(dāng)重要的作用,在國際工程中一般施工索賠額都要達(dá)到合同價(jià)款的10—15%,個(gè)別情況甚至更多。為更好地處理好建設(shè)工程中的索賠問題,須從加強(qiáng)工程項(xiàng)目建設(shè)施工計(jì)劃和施工合同管理、加強(qiáng)人員培訓(xùn)等方面入手,積極探索、實(shí)踐。 參 考 文 獻(xiàn) [1]鄔媛,殷煥武,我國建筑行業(yè)索賠現(xiàn)狀及對(duì)策分析[J].經(jīng)濟(jì)師,2006,(3). [2]徐偉, 金福安, 陳連杰.建設(shè)工程監(jiān)理規(guī)范實(shí)施手冊(cè)[M].北京:中國工業(yè)建筑出版社,2001. [3]董成海,張建生.淺析施工合同管理的問題及對(duì)策[J].建筑管理現(xiàn)代化,2001,(1). [4]成虎.建筑工程合同管理實(shí)用大全[M].北京:中國建筑工業(yè)出版社,2000,(1). 9
- 溫馨提示:
1: 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
2: 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
3.本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
5. 裝配圖網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 語文部編版《端午粽》課件2
- 秋的思念最新課件
- 20套清新商務(wù)日歷圖表合集一課件
- 簡(jiǎn)歷篩選技巧教學(xué)課件
- 《圖形創(chuàng)意設(shè)計(jì)》【初中美術(shù)教學(xué)課件】
- 部編新版人教版一年級(jí)下冊(cè)姓氏歌課件
- 西師大版六年級(jí)數(shù)學(xué)下冊(cè)總復(fù)習(xí)(5)---比和比例
- 藥物過敏反應(yīng)及處理流程ppt
- 人教版《道德與法治》九年級(jí)上冊(cè)42《凝聚法治共識(shí)》課件_參考
- 蘇教版二年級(jí)數(shù)學(xué)下冊(cè)第六單元--兩、三位數(shù)的加法和減法第7課時(shí)---練習(xí)七課件
- 蘇教版小學(xué)數(shù)學(xué)五年級(jí)下冊(cè)《方程的認(rèn)識(shí)》課件
- 國培計(jì)劃項(xiàng)目匯報(bào)模板
- 藏羚羊跪拜王春華
- 危重病人護(hù)理查房
- 中醫(yī)體質(zhì)分類及其辨證調(diào)護(hù)